Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

Yo_Mama_Been_Loggin

(108,136 posts)
Sat Apr 16, 2022, 08:00 PM Apr 2022

First of final concrete pours for West Seattle Bridge begin

The first of the final pours of specialized concrete needed to strengthen and repair the West Seattle Bridge was poured Saturday morning.

On Saturday, 35 cubic yards of concrete were poured. Bridge repairs will require 245 cubic yards, or about 30 truckloads, of the specialized concrete in total.

Crews also recently received two truckloads of non-structural concrete for the bridge’s new expansion joints and SDOT completed the final core drills through the bridge’s pier structures.

SDOT says it will be able to revisit its schedule for completing the bridge repairs once the concrete pours are completed and the work is inspected.