Related: About this forumNREL Report Firms Up Land-Use Requirements of Solar (1,000 homes require 32 acres)
(News release from Federal Research Lab, copyright concerns are nil.)
http://www.nrel.gov/news/press/2013/2269.html
[font face=Serif]News Release NR-4413
[font size=5]NREL Report Firms Up Land-Use Requirements of Solar[/font]
[font size=4]Study shows solar for 1,000 homes would require 32 acres[/font]
July 30, 2013
[font size=3]The Energy Departments National Renewable Energy Laboratory (NREL) has published a report on the land use requirements of solar power plants based on actual land-use practices from existing solar facilities.
Having real data from a majority of the solar plants in the United States will help people make proper comparisons and informed decisions, lead author Sean Ong said. The report, Land-use Requirements for Solar Power Plants in the United States, (PDF) was written with NREL colleagues Clinton Campbell, Robert Margolis, Paul Denholm and Garvin Heath.
Ong gathered data from 72% of the solar power plants installed or under construction in the United States. Among the findings:
The numbers arent good news or bad news, Denholm said. Its just that there was not an understanding of actual land-use requirements before this work. However, we were happy to find out that many of the solar land use ranges and estimates used in the literature are very close to actual solar land use requirements that we found.
These land-use estimates can also be compared with other energy-production land uses. For example, a study by Vasilis Fthenakis and Hung Chul Kim of Columbia University (2009) found that, on a life-cycle electricity-output basisincluding direct and indirect land transformationutility-scale PV in the U.S. Southwest requires less land than the average U.S. power plant using surface-mined coal.
[/font][/font]
[font size=5]NREL Report Firms Up Land-Use Requirements of Solar[/font]
[font size=4]Study shows solar for 1,000 homes would require 32 acres[/font]
July 30, 2013
[font size=3]The Energy Departments National Renewable Energy Laboratory (NREL) has published a report on the land use requirements of solar power plants based on actual land-use practices from existing solar facilities.
Having real data from a majority of the solar plants in the United States will help people make proper comparisons and informed decisions, lead author Sean Ong said. The report, Land-use Requirements for Solar Power Plants in the United States, (PDF) was written with NREL colleagues Clinton Campbell, Robert Margolis, Paul Denholm and Garvin Heath.
Ong gathered data from 72% of the solar power plants installed or under construction in the United States. Among the findings:
- A large fixed tilt photovoltaic (PV) plant that generates 1 gigawatt-hour per year requires, on average, 2.8 acres for the solar panels. This means that a solar power plant that provides all of the electricity for 1,000 homes would require 32 acres of land.
- Small single-axis PV systems require on average 2.9 acres per annual gigawatt-hour or 3.8 acres when considering all unused area that falls inside the project boundary.
- Concentrating solar power plants require on average 2.7 acres for solar collectors and other equipment per annual gigawatt-hour; 3.5 acres for all land enclosed within the project boundary.
The numbers arent good news or bad news, Denholm said. Its just that there was not an understanding of actual land-use requirements before this work. However, we were happy to find out that many of the solar land use ranges and estimates used in the literature are very close to actual solar land use requirements that we found.
These land-use estimates can also be compared with other energy-production land uses. For example, a study by Vasilis Fthenakis and Hung Chul Kim of Columbia University (2009) found that, on a life-cycle electricity-output basisincluding direct and indirect land transformationutility-scale PV in the U.S. Southwest requires less land than the average U.S. power plant using surface-mined coal.
[/font][/font]
InfoView thread info, including edit history
TrashPut this thread in your Trash Can (My DU » Trash Can)
BookmarkAdd this thread to your Bookmarks (My DU » Bookmarks)
0 replies, 726 views
ShareGet links to this post and/or share on social media
AlertAlert this post for a rule violation
PowersThere are no powers you can use on this post
EditCannot edit other people's posts
ReplyReply to this post
EditCannot edit other people's posts
Rec (2)
ReplyReply to this post