http://www.nytimes.com/2011/04/18/world/asia/18japan.html?partner=rss&emc=rssTokyo Electric Power Company said Sunday that it hopes to bring the reactors at its hobbled Fukushima Daiichi nuclear power plant into a stable state known as cold shutdown within the next nine months, during which the three damaged reactor buildings at the facility will be covered.
Enlarge This Image
The goals are part of a two-part plan that represents Tokyo Electric’s most concrete timetable yet for controlling the reactors and improving safety conditions at the plant, which was damaged by 15-meter-high tsunami waves on March 11.
<snip>
The first part of the plan would take about three months and include installing a cooling system to lower the temperature in the reactors and spent fuel pools, as well as reducing radiation in the surrounding area, said Tsunehisa Katsumata, the chairman of Tokyo Electric.
The second part, which would take up to six more months, would include more pumping of water, the introduction of a heat removal system and reducing the amount of contaminated water. The wreckage from the three damaged buildings would then be removed and the buildings covered.
<more>